ESDM Tetapkan Kuota PLTS Atap, PLN Diminta Lakukan Ini

Atikah Umiyani, Jurnalis
Selasa 04 Juni 2024 19:53 WIB
ESDM Tetapkan Kuota PLTS Atap. (Foto: Okezone.com)
Share :

Kalimantan Utara

2024: 0,8 MW

2025: 1,1 MW

2026: 1,9 MW

2027: 2,0 MW

2028: 2,2 MW

Jawa Madura Bali

2024: 825 MW

2025: 900 MW

2026: 910 MW

2027: 1.010 MW

2028: 1.400 MW

Sulawesi Utara dan Gorontalo (Sulutgo)

2024: 0,2 MW

2025: 0,4 MW

2026: 0,6 MW

2027: 0,8 MW

2028: 1,0 MW

Sulawesi Bagian Selatan (Sulbagsel)

2024: 8 MW

2025: 10 MW

2026: 12 MW

2027: 14 MW

2028: 16 MW

Maluku dan Maluku Utara

2024: 0,7 MW

2025: 1 MW

2026: 1,2 MW

2027: 1,4 MW

2028: 1,7 MW

Papua dan Papua Barat

2024: 0,8 MW

2025: 1,1 MW

2026: 1,3 MW

2027: 1,6 MW

2028: 1,9 MW

Nusa Tenggara Barat

2024: 0,9 MW

2025: 1,2 MW

2026: 1,5 MW

2027: 1,8 MW

2028: 2,2 MW

Nusa Tenggara Timur

2024: 0,6 MW

2025: 0,7 MW

2026: 0,9 MW

2027: 1,1 MW

2028: 1,3 MW

(Feby Novalius)