Ketiga, tol Palembang-Indralaya seksi I (Palembang-Pamulutan) 7,75 km, jadwal laik fungsi 5-6 September 2017, sertifikat laik operasi 14 September 2017, rencana peresmian minggu III September tanggal 18-23 September 2017.
Keempat, tol Medan-Kualanamu-Tebing Tinggi 41,6 km, jadwal laik fungsi 12-23 September 2017, sertifikat laik operasi 20 September 2017, rencana peresmian minggu IV September tanggal 25-30 September 2017.
Kelima, tol Medan-Binjai seksi 2 dan 3 (Helvetia-Binjai) 10,46 km, jadwal laik fungsi 14-15 September 2017, sertifikat laik operasi 22 September 2017, rencana peresmian minggu IV September tanggal 25-30 September 2017.